The Alamin Construction Company constructed the 262.00m long and 10m wide Pre-Stressed Concrete Girder Bridge (1st Dholeshwari Bridge) on cast-in-situ bored pile foundation at 17th km of Dhaka Khulna Road under Munshigonj Road Division.
Client: Roads and Highways Department, Ministry of Communication. Government of Bangladesh.
Salient Features:
- Pre Stressed Concrete Girder & RCC Bridge.
- Approach road.
- 3)Earth Work, flexible pavement, asphalt concrete work
- Piling Work
- Land based pile (760mm dia 32m long cast in situ bored pile)
- Water based pile by berge mounted rig (1000mm dia 35m long cast in situ bored pile)
- Total nos of pile 111 Nos.
- Temporary jetty for pre-stressing work
- Length of bridge 262m
- Width 10m (2 lane)
- 6 spans
- 30 PC Girders
- 5 Piers.
- Abutment 2 nos. and counter-fort type.